Suki Kinari Hydro Project

 
Country / Region

 

Pakistan

 

 
Project Profile
 
CGGC Suki Kinari hydropower project locates above Kunhar River,district manshera,KPK province of Pakistan,the elevation of which is between 1300m and 2400m.the dam site of SK project has a distance of 256km from islamabad. The total gross installed capacity of SK project is 873.508 MW with the supply of 4 sets of Impiles turbines. The total investment of SK project is 1.96 billion dollar with 6 years construction period. As an EPC project ,the Contract price of this project is 1.314 billion dollar. This project composes of Dam Spillway,intake,headrace tunnel,surge branch,Pressing piping,power house,tailrace tunnel and other main building.
 
 
Application of OVM Product / Service

 

Water Reserve and Hydropower;Hydropower Station Pier;Post-tensioned Prestressed Construction Equipment;Suoervision or Technical Service,OVM;OVM Geotechnical Anchor Cable,Anchor Bar